GAO Finds Cost Growth, Weak Oversight Under DOE Nuclear Cleanup Contract Model

Дата публикации: 30-07-2026 11:38:09

Seven years after overhauling how it procures nuclear waste cleanup, the Energy Dept. still cannot demonstrate the new approach is delivering better results, a federal audit concludes.

Основное содержимое страницы с новостью.

A federal audit made public July 29 found more than $500 million in increased contract values and uneven cleanup results under the U.S. Dept. of Energy’s contracting model for nuclear waste remediation, adopted in 2019, concluding the agency still cannot determine if it has improved project delivery.

DOE's Office of Environmental Management adopted the End State Contract Model to divide complex cleanup work into task orders with defined end states intended to "move sites toward completion, manage cost and schedule performance, and reduce [agency] environmental liability."

After reviewing the model's first five years, the U.S. Government Accountability Office concluded it remains unclear if the approach is an improvement over DOE's previous contracting model.

The audit examined 57 task orders worth nearly $20 billion awarded through March 31, 2025, across nine cleanup contracts at eight U.S. sites formerly used for nuclear weapons production. About half—29 task orders—included defined end states, while the remainder covered transition, support or cleanup work that had not yet established them.


Costs Rose as Scope Changed

Among 18 selected task orders, GAO found more than $500 million in increased contract values after award, largely because DOE expanded work scopes, extended schedules or otherwise changed requirements during execution.

The largest dollar increases occurred at Oak Ridge Reservation in Tennessee, where an End States Phase-In order increased by $216.7 million, or 45%, and work to construct and commission the Outfall 200 Mercury Treatment Facility increased by $25.8 million, or nearly 139%.

At the Nevada National Security Site, an environmental operations order covering groundwater testing and facility closure cost grew by nearly 150%, largely through planned extensions rather than new task orders.

Looking for quick answers on construction and engineering topics?
Try Ask ENR, our new smart AI search tool.
Ask ENR

GAO also found contract type appeared to influence performance. The firm-fixed-price and cost-plus-incentive-fee task orders it reviewed averaged slightly more than 2% growth, while cost-plus-fixed-fee and cost-plus-award-fee task orders averaged roughly 50%, reflecting the greater financial risk retained by the government under those structures.

Higher contract values did not consistently produce the cleanup outcomes DOE intended. Of six completed task orders with defined end states that GAO reviewed, only two achieved those outcomes as originally planned. One fell short of its cleanup target, while three others had work reduced or transferred to subsequent task orders after award.

At the Hanford site in Washington, GAO found DOE modified the required scope for 12 of 22 completed end states under a $1.8-billion task order performed by Central Plateau Cleanup Co., transferred about $19 million of work into a later task order and lacked sufficient documentation to determine whether three additional end states had been completed.


Map of DOE nuclear cleanup sites operating under the end-state contracting model across the United States.

A Government Accountability Office map identifies the Department of Energy's active environmental cleanup sites operating under the agency's end-state contracting model as of March 31, 2025. A July 29 GAO audit found DOE has not yet demonstrated the approach is improving project delivery or achieving its intended results.

Image: U.S. Government Accountiability Office


Oversight Fell Short

GAO said the performance problems coincided with weak headquarters oversight. Six selected task orders at Hanford, Oak Ridge and Nevada began before DOE and contractors had finalized scope, cost, schedule and fee negotiations, and four exceeded the generally required 180-day deadline for definitization.

Read More GAO Report —
Nuclear Waste Cleanup:
DOE Needs to Better Use End State Contracts to Achieve Intended Results

The audit also found "headquarters did not provide adequate oversight" to ensure task orders achieved their defined end states. Contractors played a significant role in developing end states and planning work after master contracts were awarded, making federal oversight more important because task-order work proceeded without further competition.

GAO recommended that the Energy Dept. strengthen headquarters oversight, improve procurement reporting and cost estimating, identify the causes of increased task-order values and ensure undefined task orders are finalized on time. DOE concurred with five of the six recommendations and partially concurred with the one addressing cost growth.

In its response, the Energy Dept. argued that increased task-order values do not necessarily represent uncontrolled overruns because "the complexity of [the] mission can often result in requirement changes" that reduce environmental risk or improve long-term efficiency.

GAO disagreed, saying DOE still needs to identify and address the underlying causes of increased task-order values, including government decisions affecting scope and estimating. Without stronger oversight, the department "cannot assess how well it is meeting program goals," the audit concluded.

Схожие новости

#Наименование новостиТональностьИнформативностьДата публикации
1The watchdog gets watched: GAO’s hiring process length faces scrutiny 010.8619-08-2026
2МАГАТЭ и Ростехнадзор не выявили недостатков в спецводоочистке на ЗАЭС0014-04-2025
3Счетная палата увидела формальное исполнение половины госпрограмм в России0013-05-2023
4На Калининской АЭС отмечен высокий уровень проведения целевых инструктажей0005-08-2019
5Счетная палата выявила систематические недочеты и нарушения при проверке Минпромторга0016-03-2021
6На ЗАЭС не выявили нарушений в обращении с жидкими радиоактивными отходами0017-09-2025
7Ингушское УФАС выявило 44 нарушения контрактной системы при реализации нацпроектов0025-07-2019
8Счетная палата проверила расходы на развитие Единой глубоководной системы-2729-06-2026
9Главу Водоканала Петербурга отправили в отставку после проверки контрольно-счетной палаты0018-03-2019
10Росфинмониторинг выявил 6 тыс. недобросовестных исполнителей контрактов по нацпроектам0016-03-2021

Классификация: . Схожих патентов: 0. Схожих новостей: 10. Тональность: 0. Информативность: 8.52. Источник: www.enr.com.