Kolkata Metro Orange Line clears 6 year Chingrighata delayKolkata Metro Orange Line Chingrighata viaduct completed

KOLKATA (Metro Rail News): Kolkata Metro Orange Line has overcome a major construction challenge at Chingrighata after more than six years of delays. Completing the 366-meter viaduct gap could now allow Metro services between New Garia and Sector V. 

Rail Vikas Nigam Ltd (RVNL) is handling the 32-kilometer New Garia-Airport corridor. On Sunday, they placed the final 31-meter concrete deck slab at Chingrighata. This viaduct work closes a long-standing gap at one of the busiest intersections on the route.

Chingrighata work completed in 90 days

The construction team finished launching the girder at the intersection in about 90 days. The new viaduct rises around 12 meters above the road. RVNL hoisted the national flag on the newly completed viaduct on Saturday to celebrate this construction milestone. Finishing this section is significant because Chingrighata was one of the biggest obstacles to the Kolkata Metro’s Orange Line progress.

The weekly brief metro & rail professionals read.

New Garia-Sector V services could start by December

General Manager of Kolkata Metro, Prem Sagar Gupta recently mentioned that the organization is working toward a December 31 deadline to open the Beleghata (Metropolitan), IT Centre (Sector V) section. Once this section opens, commuters could travel from New Garia to Sector V in about 30 minutes. The Orange Line is part of the larger 32-kilometer New Garia-Airport Metro corridor, which RVNL is implementing.

How the Chingrighata bottleneck was resolved 

Construction at the intersection faced several technical and administrative challenges. The main issue focused on Pier 318, which was planned near the center of the Chingrighata crossing. The timeline shows the prolonged delays:

  • 2020: Construction work at Chingrighata faced difficulties.  
  • August 2020: IIT Kharagpur approved the design for the proposed Pier 318.  
  • May 2023: The state government issued the NOC for constructing the pier.  
  • December 2024: RVNL completed a new road that helped divert traffic during construction.  
  • February 2, 2025: RVNL awaited a traffic block to carry out the needed work.  
  • Mid-May 2026: Concrete girders were erected across the crossing over two weekends.  
  • August 2026: The final deck slab was placed, completing the 366-meter viaduct gap.

Police clearance was another hurdle

Even with technical approvals and the state NOC, RVNL could not immediately continue with construction. Traffic clearance from Kolkata Police was delayed for about 15 months. This matter also arose before the Calcutta High Court, which frequently sought updates on the situation. The eventual traffic arrangements enabled RVNL to carry out the girder launching and finish the remaining viaduct work.

Clearing the Chingrighata bottleneck removes one of the longest-running construction challenges for the Orange Line. If the remaining work and approvals stay on schedule, the New Garia, Sector V section could offer a much quicker connection between south Kolkata and the city’s eastern IT and business hub.

Also Read: Big Breakthrough for Kolkata Metro’s Purple Line as TBM Divya Reaches Victoria Metro Station 

Guide
Kolkata Metro: the complete guideAll corridors, status, routes and the latest news in one place →

Схожие новости

#Наименование новостиТональностьИнформативностьДата публикации
1 Comment on Chennai Metro expedites construction work on Purple Line under Phase-II by Karthik 012.4919-07-2026
2 Comment on Bengaluru Metro to connect Tamil Nadu Border: BMRCL plans 9 new stations  by Satish 013.6717-08-2026
3 Comment on DMRC floats electrical tender for Rithala-Kundli Corridor (Phase IV) by davinder singh 015.2618-07-2026
4 Comment on Bengaluru Suburban Rail: Double Decker Flyover to approach space limitation  by STANITE U V 07.1319-07-2026
5Поезда на красной линии московского метро задерживаются на юго-западном участке0006-09-2018
6Community eager for accessible playground in Youngstown after construction delays01028-07-2026
7Mumbai Metro: MMRDA awards ₹29.63 cr contract for Signage Works on Line 6 & 7A017.8912-08-2026
8Что случилось сегодня на фиолетовой ветке метро? Сегодня на фиолетовой ...0713-07-2026
9Движение трамваев в центре Москвы восстановлено0004-09-2019
10Centre yet again rules out Metro Rail for Coimbatore and Madurai; recommends BRTS06.9426-07-2026

Классификация: Мнения. Схожих патентов: 0. Схожих новостей: 10. Тональность: 0. Информативность: 9.37. Источник: www.metrorailnews.in.